Reschedule Dependencies when moving the task to an earlier date.
under review
Amy Lee
Comment from support: When I change the date of a task to a later date, the dependencies are moved back to a later date too, but when I move the date of the task to an earlier date, the dependencies don't change?
Log In
Emily Anthony
This is critical. My team is really struggling with this right now and we're beyond frustrated. This borderline makes the tool unusable.
B
Brandon De Young
This is such a critical change that is needed, as many others below have stated! I agree that it truly seems more like a bug than a feature to not allow dependencies to auto-adjust when the blocking task is moved earlier. The current design should be the exception. Having to manually adjust allllll of the dependent tasks that come after is extremely tedious, especially for very complex workflows! Any ETA to make this change?? Is there not even an automation or some workaround either??
Juan Grandas
Merged in a post:
Reschedule Dependencies in reverse
Cody Boyce
It'd be great if this ClickApp could be enabled in reverse order - meaning, if the last task in a chain of dependencies has a date change, all previous tasks that are blocking it are reschedule automatically. Our workflow may be unique, but all task due dates are set based on the very last task in the chain.
D
Daniel Oberhaus
Are there plans to move this into development or workarounds using automations?
This is such a critically important feature for us we may have to migrate platforms because of it.
A
Adam Roy
This feature is critical to my business and many others in this thread. This seems like more of a bug than a feature request considering how important this is. It's a major feature that's missing.
Any update on when this could get into development?
I
Inna Vasiljeva
Yes please! This is crucial for me and my team to be able to work in ClickUp
Juan Grandas
Merged in a post:
Automatically Remap Dependency Due Dates
J
Jasmine Penny
When changing the due date on a task, add the option to remap the due dates on any dependent tasks. I want to avoid having to manually change the due dates for tasks that are waiting on another one if I've just changed the date of the task that's blocking.
Juan Grandas
under review
J
Joachim Weber
We are new with ClickUp enterprise and we can’t believe that a basic request like this is open for over 4 years now.🤷🏻♂️
Sara Spangler
Any update on this? Without being able to move due dates earlier & have dependencies automatically update, this feature becomes a bit useless. One mistake and your entire schedule is unusable. There also needs to be flexibility in due dates moving later OR earlier.