Reschedule Dependencies On/Off in Gantt View
Paul
When in Gantt View, it would be good to be able to instantly see, on the screen, whether Reschedule Dependencies is turned on or off.
Currently you need to click on Customize > Gantt Options to see if it's selected or not.
With a complex project it's dangerous to edit anything in Gantt View until you're sure the Reschedule Dependencies setting is on or off. Having a direct option to switch this off/on without needing to go to Customize > Gantt Options would be even better.
Log In
P
PC
I forgot that I already requested this 8 months ago. At least it would be good to be good to have Reschedule Dependencies easier to access than the current sequence, which is now:
Customise > Layout Options > Reschedule Dependencies.
When setting up, or resetting a big project I still say that it would be good to have easier access to switch this setting, and to see whether it is currently on or off.