Project/List % Complete
Devonte Nabors
Our team uses project completion percentages to calculate month-end billing, so having an overall % Complete value displayed at the top of each List would provide significant value for project tracking, forecasting, and billing.
Ideally, ClickUp would support multiple calculation methods so organizations can choose the approach that best fits their business needs.
One option would be a simple calculation based on completed tasks divided by total tasks.
Another option would be a weighted calculation based on task effort, such as estimated hours or duration, where larger tasks have a greater impact on the overall project completion percentage than smaller tasks. This provides a more accurate representation of project progress.
A third option would calculate project completion based on actual hours logged compared to the total estimated hours for the project, allowing the completion percentage to increase as work is performed and time is tracked.