I have reccurent processes that I have to do and sometimes I have to do them more than once a day. Since it's not possible to add multiple due dates to a single task I have created one task per hour that I have to complete the task by every day (and then set each task's due date to reccurent every day). However when I create a Gantt view all of these tasks (that should only be one task) appear in different rows when I wanted them to show up as a single row. I have tried creating a parent task in order for them to be grouped in some way but this still does not make them show up in a single row.