Pieter Koch
Baseline for planning views (Gantt chart) is not a nice to have but essential! the chart is pretty useless without this from a PM point. Please can you add this else would need to look at something else.
David Mason
Specifically being able to save multiple 'snapshots' or a history of the 'baselines' and selecting which to compare vs the live plan would be very value added such that the project manager can visualise slippage vs key points in the plan.
bianca r
Hi Anthony, any update on this or proposed dates for implementation?
Anthony C.
Merged in a post:
Save gantt chart to later show changes with respect to original
M
Marco Delgado Schwartz
It is great that I can change the start and due dates on the gantt chart, and relocate a task to happen at a different time. However it would be nice if the gantt chart could be saved, so that one can compare to it later with the changes that have been made.
Anthony C.
Merged in a post:
Display real work times instead of plans and estimates in gantt and timeline
J
Jan Zalewski
mak it possible to make those views display the period in which task was actually worked on (maybe based on first edit and close date or first and last time tracked element) as an alternative or even overlap on top of showing planned dates
it could also serve as a way to visualise this
S
Simone Filippin
Nice to know that this feature is PLANNED, "Gantt improvement" might also involve this?
K
Kai Appel
That is one of the most important features! Would be brilliant to have! Can't await to get this functionality. Thanks!
Lucas Antunes
About the baseline in the Gantt view. Is there already a prospect for at least a trial version?
Anthony C.
Merged in a post:
Due date/Rescheduling tracking
R
Regis Massie
When using gantt/timeline view, it would be VERY useful to view any rescheduled tasks due dates visually. A little bit like slack time, but on the tasks/issues. One way to do that would be to create a custon "Original Due Date" that is set via automation from another boolean field "Final Something(dates, adjustments)". When you tick this box, it sets the Original Due Date. After this, if you change the due date, we still have the original one - so we could set the charts to set custom colors for the time range between the 2 dates. The automation part works, but I can't set custom colors on tasks for a date range.