Allow setting of ad-hoc non-working days and/or public holidays
L
Lee Michelle
Like other sheets, it would be good to the ability to either (1) float in the list of public holidays of a country, or (2) allow manual input of non-working days; And then highlight these days on the Gantt Chart or other views, so that in terms of scheduling, these days are not calculated in terms of billings or other matters.
It will also be using for, say in the future when you are putting in a 'Days/Hours Left' column on Gantt, then this value won't include non-working days.
Thank you.
Log In
G
Galanda A Brooker
I believe that adding the option for the 4 most predominate religions to have a calendar that can be added for view purposes within ClickUp is relevant to this request as well. https://clickup.canny.io/feature-requests/p/add-religious-holidays
R
Ridlo Akbar
it's 2024 and we still don't have it.
Wendy Conley
It would be extremely beneficial to manually add in our holidays or non-working days so when project schedules are adjusted (as they always are) this is accommodated without me having to manually change each and every reoccurring project schedule.
Please also add a function to automatically excluding weekends so project schedules can accommodate accordingly. It would be ideal if this was just a default to exclude weekends and have an option to add in weekends if needed.
A
Admin Calder
With a Gantt chart feature there isn't much value in the scheduling if it doesn't allow you to plan around blocked days such as public holidays and work holidays.
Would be useful to have a calendar that could set time periods as non working so the different views accurately reflected the working days.
Would also be handy to be able to toggle the feature per project to mark the period as no work (i.e. shade the section and mark as no work) or show them as working days but visually show them in the timeline (i.e. shade the section, tasks scheduled as usual)
Caoimhe Roddy
non-working days need to be addressed in general to be useful for features such as Workload view and Sprint. As a 4-day-week company, a lot of how Clickup functions assumes we work 5 days even when non-working days are set correctly.
B
Brian Shen
B
Brian Shen
Merged in a post:
Designate non-working days in any project schedule
D
Debbie O'Meara
When setting up a project schedule, I'd like to be able to automatically exclude weekends (and other non-working days). That way if I change the start date of a task, it can keep the number of business days constant and ensure my due date doesn't fall on a weekend.
Till Scheffczyk
This would be wonderful for Canadian Holidays as well.
B
Brian Shen
B
Brian Shen
Thanks for the feedback! I will merge this with the main request.
Load More
→