Add "Shift Dates" Option to Multitask Toolbar
Nathan Boyer
Often, I need to shift all task due dates in a list by a month. There is currently no method to easily achieve this. The multitasking toolbar can set all tasks to a single new due date, or you can go down the list and change each task due date separately. However, there is no way to delay the project due dates and keep their relative date spacing.
I make heavy use of the "remap due dates" feature of list/folder templates. However, once the template is applied, there is no way to later shift the dates to accommodate upstream project delays. (You might suggest task dependencies, but often the delays are from external sources not tracked in ClickUp, and a large chain of sequential dependencies running down a list creates more issues than benefits.)