I would like the ability to assign a task to a Team in clickup, and have the effort split between all team members. Today, the total effort is assigned to EVERY team member.
In my ideal scenario, assigning a 5-day task of 25h to a team of 5 people would mean that each person is allocated 1h/day.
The purpose of this request is to be able to assign work to a team/role without know who the specific individual will be. The effort should be load balanced between the team members so that future capacity/planning is achievable.
An alternative to this is a team roll-up that shows something like 5 team members with 8h/day means 48h/day for the team. I can assign a task to the "team" without know who the exact person doing the work would be, and this would deduct from the team capacity.
This would allow me to be able to plan a project a few weeks in advance and see when the team could theoretically start it based on the Team's availability.